RESEARCH ARTICLE
Investigating the challenges related to combining BIM and Last Planner System on construction sites
Conrad BOTON(), Yaya PITTI, Daniel FORGUES, Ivanka IORDANOVA
Department of Construction Engineering, École de Technologie Supérieure, Montréal, Canada
 Download: PDF(930 KB)   HTML
 Export: BibTeX | EndNote | Reference Manager | ProCite | RefWorks
Abstract

The construction industry is facing a gradual but important transformation toward more productivity and collaboration. In this framework, two major approaches are often cited in the literature as having the potential to improve the practices in the industry: Building Information Modeling (BIM) and Lean Construction. Several scientific studies have demonstrated the synergy of these two approaches and very recent research has reported positive results from the use of software applications as support for their implementation on construction sites. However, the stakes of such integration have been very little studied. This article presents the results of a research project conducted within a general contractor firm that decided to implement BIM and Last Planner System (LPS) on its construction sites. The research uses a four-stage action research approach, including the characterization of the research issue, the establishment of an action plan, its implementation and its evaluation. Compared to recent related studies, the research is less enthusiastic. While it highlights the need for new tools to improve production planning and control, it also points to a strong resistance to change by practitioners at the site. They emphasize the necessity for adequate pre-service training and the need for new resources that can work full-time on the ongoing training of site teams. In addition, some limitations of the tool lead workers to believe that it can quickly become a factor that slows down their daily work rather than improving it. Based on the advice of professionals, the paper formulates some recommendations to the industry, the researchers and the software developers.

Keywords Building Information Modeling      Last Planner System      construction site      lean construction     
Corresponding Author(s): Conrad BOTON   
Just Accepted Date: 17 December 2019   Online First Date: 27 February 2020    Issue Date: 25 March 2021
 Cite this article:   
Conrad BOTON,Yaya PITTI,Daniel FORGUES, et al. Investigating the challenges related to combining BIM and Last Planner System on construction sites[J]. Front. Eng, 2021, 8(2): 172-182.
 URL:  
https://academic.hep.com.cn/fem/EN/10.1007/s42524-019-0086-4
https://academic.hep.com.cn/fem/EN/Y2021/V8/I2/172
Fig.1  The main steps of action research.
Fig.2  Overview of the steps of the research.
Fig.3  Exterior and interior views of the building.
InterviewsIntervieweesDatesSubjects
(1)(2)(3)(4)(5)(6)(7)
# 1Project manager2018-11-06XXX
# 2Assistant project manager2018-11-06XXXXXX
# 3Superintendent2018-11-06XXXX
# 4Project manager2018-11-07XXX
# 5Planning officer2018-11-07XXX
# 6Superintendent2018-11-08XXXX
# 7Project manager2018-11-08X
Tab.1  Details of the interviews with the discussed subjects
Fig.4  Planning process, with BIM 360 Plan.
Fig.5  Control process, with VisiLean.
1 A O AlSehaimi, P Tzortzopoulos Fazenda, L Koskela (2014). Improving construction management practice with the Last Planner System: A case study. Engineering, Construction, and Architectural Management, 21(1): 51–64
https://doi.org/10.1108/ECAM-03-2012-0032
2 Y Arayici, P Coates, L Koskela, M Kagioglou, C Usher, K O’Reilly (2011a). BIM adoption and implementation for architectural practices. Structural Survey, 29(1): 7–25
https://doi.org/10.1108/02630801111118377
3 Y Arayici, P Coates, L Koskela, M Kagioglou, C Usher, K O’Reilly (2011b). Technology adoption in the BIM implementation for lean architectural practice. Automation in Construction, 20(2): 189–195
https://doi.org/10.1016/j.autcon.2010.09.016
4 G Ballard, G Howell (1997). Toward construction JIT. In: Alarcón L F, ed. Lean Construction. Rotterdam: Balkema, 291–300
5 G Ballard, G Howell (2004). An update on Last Planner. In: Proceedings of the 11th Annual Conference of the International Group for Lean Construction. Blacksburg, VA
6 H G Ballard (1994). The Last Planner. In: Spring Conference of the Northern California Construction Institute. Monterey, CA
7 H G Ballard (2000). The Last Planner System of Production Control. Dissertation for the Doctoral Degree. Birmingham: University of Birmingham
8 R Baskerville, M D Myers (2004). Special issue on action research in information systems: Making IS research relevant to practice: Foreword. Management Information Systems Quarterly, 28(3): 329–335
https://doi.org/10.2307/25148642
9 F Berroir, L Harbouche, C Boton (2015). Top down vs. bottom up approaches regarding the implementation of Lean Construction through a French case study. In: Proceedings of the 23rd Annual Conference of the International Group for Lean Construction. Perth, Australia: 73–82
10 M Bilandzic, J Venable (2011). Towards participatory action design research: Adapting action research and design science research methods for urban informatics. Journal of Community Informatics, 7(3): 1–17
11 C Boton, D Forgues (2018). Practices and processes in BIM projects: An exploratory case study. Advances in Civil Engineering, 2018: 1–12
https://doi.org/10.1155/2018/7259659
12 C Boton, D Forgues, G Halin (2018). A framework for Building Information Modeling implementation in engineering education. Canadian Journal of Civil Engineering, 45(10): 866–877
https://doi.org/10.1139/cjce-2018-0047
13 C Boton, G Halin, S Kubicki (2012). A metamodel to describe nD CAD visualization as coordinated multiple views. In: Luo Y, ed. Cooperative Design, Visualization, and Engineering. CDVE 2012. Lecture Notes in Computer Science. Berlin, Heidelberg: Springer, vol. 7467, 219–226
14 C Boton, S Kubicki, G Halin (2013). Designing adapted visualization for collaborative 4D applications. Automation in Construction, 36: 152–167
https://doi.org/10.1016/j.autcon.2013.09.003
15 C Boton, L Rivest, D Forgues, J Jupp (2016). Comparing PLM and BIM from the product structure standpoint. In: Product Lifecycle Management for Digital Transformation of Industries. PLM 2016. IFIP Advances in Information and Communication Technology. Cham: Springer, vol. 492, 443–453
16 C Boton, L Rivest, D Forgues, J R Jupp (2018b). Comparison of shipbuilding and construction industries from the product structure standpoint. International Journal of Product Lifecycle Management, 11(3): 191–220
https://doi.org/10.1504/IJPLM.2018.094714
17 M Broadbent, P Weill (1993). Improving business and information strategy alignment: Learning from the banking industry. IBM Systems Journal, 32(1): 162–179
https://doi.org/10.1147/sj.321.0162
18 Y M Cheng (2014). An exploration into cost-influencing factors on construction projects. International Journal of Project Management, 32(5): 850–860
https://doi.org/10.1016/j.ijproman.2013.10.003
19 J Clemente, N Cachadinha (2013). Bim-Lean synergies in the management on mep works in public facilities of intensive use—A case study. In: Proceedings of the 21st Annual Conference of the International Group for Lean Construction. Fortaleza, Brazil: 751–760
20 B Dave, S Boddy, L Koskela (2013). Challenges and opportunities in implementing Lean and BIM on an infrastructure project. In: Proceedings of the 21st Annual Conference of the International Group for Lean Construction. Fortaleza, Brazil: 60–69
21 B Dave, L J Koskela (2011). Visilean: Designing a production management system with lean and BIM. In: Proceedings of the 19th Annual Conference of the International Group for Lean Construction. 477–487
22 H Doloi (2013). Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects. Journal of Construction Engineering and Management, 139(3): 267–279
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000621
23 R Fosse, G Ballard, M Fischer (2017). Virtual design and construction—Aligning BIM and Lean in practice. In: Proceedings of the 25th Annual Conference of the International Group for Lean Construction. 499–506
24 S Gao, S P Low (2014). Lean Construction Management: The Toyota Way. Berlin: Springer
25 O Hamdi, F Leite (2012). BIM and Lean interactions from the bim capability maturity model perspective: A case study. In: Proceedings of the 20th Annual Conference of the International Group for Lean Construction
26 F R Hamzeh, E Zankoul, C Rouhana (2015). How can ‘tasks made ready’ during lookahead planning impact reliable workflow and project duration? Construction Management and Economics, 33(4): 243–258
https://doi.org/10.1080/01446193.2015.1047878
27 J Henderson, N Venkatraman (1990). Strategic alignment: A model for organizational transformation via information technology. New York: Oxford University Press, 202–220
28 S Khan, P Tzortzopoulos (2014). Effects of the interactions between LPS and BIM on workflow in two building design projects. In: Proceedings of the 22nd Annual Conference of the International Group for Lean Construction. Oslo, Norway: vol. 2, 933–944
29 L Koskela, G Howell, G Ballard, I Tommelein (2002). The foundations of lean construction. In: Best R, de Valence G, eds. Design and Construction: Building in Value. Woburn, MA: Butterworth-Heinemann, 211–226
30 A Lee, G Aouad, R Cooper, C Fu, A Marshall-Ponting, J Tah, S Wu (2005). nD modelling—A driver or enabler for construction improvement? RICS Research Paper Series, 5(6): 1–16
31 S G Naoum (2016). Factors influencing labor productivity on construction sites. International Journal of Productivity and Performance Management, 65(3): 401–421
https://doi.org/10.1108/IJPPM-03-2015-0045
32 S Pekkola, N Nieminen (2015). Comparison of functional, structural, and dynamic business-IT alignment models: A case study. In: Proceedings of the 21st Americas Conference on Information Systems (AMCIS). 1–14
33 Y Pitti, C Boton, D Forgues (2019). Combining BIM and Last Planner on construction sites: An investigation of the related challenges. In: Skibniewski M J, Hajdu M, eds. Proceedings of the Creative Construction Conference. Budapest, Hungary: 824–829
34 E Poirier, D Forgues, S Staub-French (2016). Collaboration through innovation: Implications for expertise in the AEC sector. Construction Management and Economics, 34(11): 769–789
https://doi.org/10.1080/01446193.2016.1206660
35 S Rafael, C Eastman, G Lee, T Paul (2018). BIM Handbook: A Guide to Building Information Modeling for Owners, Designers, Engineers, Contractors, and Facility Managers. 3rd ed. Hoboken, New Jersey: Wiley
36 I A Rahman, A H Memon, A T A Karim (2013). Significant factors causing cost overruns in large construction projects in Malaysia. Journal of Applied Sciences, 13(2): 286–293
https://doi.org/10.3923/jas.2013.286.293
37 R Sabherwal, R Hirschheim, T Goles (2001). The dynamics of alignment: Insights from a punctuated equilibrium model. Organization Science, 12(2): 179–197
https://doi.org/10.1287/orsc.12.2.179.10113
38 R Sacks, L Koskela, B A Dave, R Owen (2010). Interaction of Lean and Building Information Modeling in construction. Journal of Construction Engineering and Management, 136: 968–980
39 P Saieg, E D Sotelino, D Nascimento, R G G Caiado (2018). Interactions of Building Information Modeling, Lean and sustainability on the architectural, engineering and construction industry: A systematic review. Journal of Cleaner Production, 174: 788–806
https://doi.org/10.1016/j.jclepro.2017.11.030
40 O Seppänen, G Ballard, S Pesonen (2010). The combination of Last Planner System and Location-Based Management System. Lean Construction Journal, 43–54
41 M Shelbourn, N M Bouchlaghem, C Anumba, P Carrillo (2007). Planning and implementation of effective collaboration in construction projects. Construction Innovation, 7(4): 357–377
https://doi.org/10.1108/14714170710780101
42 M Tauriainen, P Marttinen, B Dave, L Koskela (2016). BIM and lean construction change design management practices. In: Proceedings of the Creative Construction Conference. Budapest, Hungary: 668–673
43 P Teicholz (2013). Labor-productivity declines in the construction industry: Causes and remedies (a second look). AECbytes Viewpoint
44 The Computer Integrated Construction Research Program (2010). Building Information Modeling execution planning guide. Version 2.0. The Pennsylvania State University: Computer Integrated Construction Research Group
45 M A Vigneault, C Boton, H Y Chong, B Cooper-Cooke (2019). An innovative framework of 5D BIM solutions for construction cost management: A systematic review. Archives of Computational Methods in Engineering, 1–18
https://doi.org/10.1007/s11831-019-09341-z
[1] Mingyue LI, Zhuoling MA, Xi TANG. Owner-dominated building information modeling and lean construction in a megaproject[J]. Front. Eng, 2021, 8(1): 60-71.
[2] Roshan POUDEL, Borja GARCIA de SOTO, Eder MARTINEZ. Last Planner System and Scrum: Comparative analysis and suggestions for adjustments[J]. Front. Eng, 2020, 7(3): 359-372.
[3] Conrad BOTON, Éric ST-PIERRE, Gabriel LEFEBVRE. Should medium-sized contractors still implement home-made information technologies on construction sites?[J]. Front. Eng, 2020, 7(1): 142-158.
[4] Ming LU, Nicolas DIAZ, Monjurul HASAN. Proposing a “lean and green” framework for equipment cost analysis in construction[J]. Front. Eng, 2019, 6(3): 384-394.
[5] Hans VOORDIJK. Building information modeling and its impact on users in the lifeworld: a mediation perspective[J]. Front. Eng, 2019, 6(2): 193-206.
[6] Albert P. C. CHAN, Xiaozhi MA, Wen YI, Xin ZHOU, Feng XIONG. Critical review of studies on building information modeling (BIM) in project management[J]. Front. Eng, 2018, 5(3): 394-406.
[7] Hongtao ZHOU, Hongwei WANG, Wei ZENG. Smart construction site in mega construction projects: A case study on island tunneling project of Hong Kong-Zhuhai-Macao Bridge[J]. Front. Eng, 2018, 5(1): 78-87.
[8] Takashi KANETA, Shuzo FURUSAKA, Nisi DENG. Overview and problems of BIM implementation in Japan[J]. Front. Eng, 2017, 4(2): 146-155.
[9] Dongping CAO, Heng LI, Guangbin WANG. Impacts of building information modeling (BIM) implementation on design and construction performance: a resource dependence theory perspective[J]. Front. Eng, 2017, 4(1): 20-34.
[10] Qing-hua He,Ge Wang. Hotspots Evolution and Frontier Analysis of Lean Construction Research—Integrated Scientometric Analysis using the Web of Science and Scopus Databases[J]. Front. Eng, 2015, 2(2): 141-147.
[11] Wei-dong Wang,Jie Wu,Kai-jun Wang,Xin Wen. Construction Duration and Cost Simulation via Network-Program-Diagram[J]. Front. Eng, 2014, 1(2): 210-217.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed