Construction Duration and Cost Simulation via Network-Program-Diagram
Wei-dong Wang1,*(),Jie Wu2,Kai-jun Wang3,Xin Wen4
1. Department of Civil Engineering, Central South University, Changsha 410075, China
2. National Engineering Laboratory for High Speed Rail Construction, Changsha 410075, China
3. The Third Railway Survey and Design Institute Group Corporation, Tianjin 300142, China
4. Costing Department of Economic Planning Institute of the Ministry of Railways, Beijing 100038, China
 Download: PDF(1201 KB)  
 Export: BibTeX | EndNote | Reference Manager | ProCite | RefWorks
Abstract

This paper outlines the creation of a simulation model used to extrapolate duration and resource requirements needed for the construction of bridges based on a sampling of data obtained during a field research conducted on the construction process of a single bridge. A sampling of statistical data was taken during a field investigation to measure schedule and resource requirements (labor, raw materials and machinery) at various stages of a bridge construction project. This data was used to identify the probability distribution and the associated parameters for the project examined, and a simulation model was built to extrapolate the necessary schedule and resource requirements needed for various stages of similar bridge projects based on Three-Point Estimation Method of Program Evaluation and Review Technique (PERT) and Monte Carlo Method. This simulation model’s resultant data for every process in an applicable construction project can be aggregated to form overall project duration and resource requirement statistical distribution using the Critical Path Method (CPM). The whole construction process will be visualized by a 4-dimensional (4D) model of the project which is created by appending time and resource requirements and to the 3-dimensional (3D) model that is built using the Building Information Modeling (BIM) and Alternativa 3D technology. Based on the simulation results of every procedure’s duration and resource requirements, the Network Program Diagram and Gantt Chart can be drawn with Flex and ActionScript language. Furthermore, with the Network Program Diagram at the core, the 4D model can incorporate simulation’s resultant data with respect to total time and cost of the project to show the condition of resource requirements and the project’s progressing at any time.

Keywords construction duration      construction cost      activity-on-node diagram      building information modeling     
Corresponding Author(s): Wei-dong Wang   
Online First Date: 05 September 2014    Issue Date: 16 September 2014
 Cite this article:   
Wei-dong Wang,Jie Wu,Kai-jun Wang, et al. Construction Duration and Cost Simulation via Network-Program-Diagram[J]. Front. Eng, 2014, 1(2): 210-217.
 URL:  
https://academic.hep.com.cn/fem/EN/10.15302/J-FEM-2014028
https://academic.hep.com.cn/fem/EN/Y2014/V1/I2/210
1 Al-Bahar, J. F., & Crandall, K. C. (1990). Systematic risk management approach for construction project. Construction Engineering and Management, 116(4), 533-546
https://doi.org/10.1061/(ASCE)0733-9364(1990)116:3(533)
2 Azevedo, J. D., & Oliveira, S. P. (2012). A numerical comparison between quasi-Monte Carlo and sparse grid stochastic collocation methods. Communications in Computational Physics, 12(4), 1051-1069
3 Clark, C. E. (1962). The PERT model for the distribution of an activity time. Oper. Res., 10(3), 405-406
https://doi.org/10.1287/opre.10.3.405
4 Chou, J. (2011). Cost simulation in an item-based project involving construction engineering and management. Int. J. Proj. Manag., 29(6), 706-717
https://doi.org/10.1016/j.ijproman.2010.07.010
5 Cox, M. A. A (1995). Simple normal approximation to the completion time distribution for a PERT network. Int. J. Proj. Manag., 13(4), 265-270
https://doi.org/10.1016/0263-7863(95)00026-M
6 Chau, K. W., Anson M., & Zhang, J. P. (2003). Implementation of visualization as planning and scheduling tool in construction. Build Environ, 38(5), 713-719
https://doi.org/10.1016/S0360-1323(02)00239-1
7 Dino, Z., Issa, R. R. A., & Suermann, P. C. (2009). BIM’s impact on the success measures of construction projects. J. Comput. Civ. Eng., 346, 503-512
8 Ding, L., Zhou, Y., Luo, H., & Wu, X. (2012). Using no technology to develop an integrated construction management system for city rail transit construction. Autom Construct, 21, 64-73
https://doi.org/10.1016/j.autcon.2011.05.013
9 Golpayegani, S. A. H., & Emamizadeh, B. (2007). Designing work breakdown structures using modular neural networks. Decis. Support Syst., 44(1), 202-222
https://doi.org/10.1016/j.dss.2007.03.013
10 Hahn, E. D. (2007). Mixture densities for project management activity times: a robust approach to PERT. Eur. J. Oper. Res., 188(2), 450-459
https://doi.org/10.1016/j.ejor.2007.04.032
11 Heesom, D., & Mahdjoubi, L. (2004). Trends of 4D CAD applications for construction planning. Construct. Manag. Econ., 22(2), 171-182
https://doi.org/10.1080/0144619042000201376
12 Jung, Y., Woo, S. (2004). Flexible work breakdown structure for integrated cost and schedule control. J. Constr. Eng. Manage., 130(5), 616-625
https://doi.org/10.1061/(ASCE)0733-9364(2004)130:5(616)
13 Kelley, J. E. Jr. (1961). Critical-path planning and scheduling: mathematical basis. Oper. Res., 9(3), 296-320
https://doi.org/10.1287/opre.9.3.296
14 Kaplan, R. S., & Anderson, S. R. (2004). Time-driven activity-based costing. Harv. Bus. Rev., 82(11), 131-138
15 Kelley, J. E., & Walker, M. R. (1959). Critical path planning and scheduling. Proceedings of the Eastern Joint Computer Conference, 1-3
16 Malcolm, D. G., Roseboom, J. H., Clark, C. E., & Fazar, W. (1959). Application of a technique for a research and development program evaluation. Oper. Res., 7(5), 646-669
https://doi.org/10.1287/opre.7.5.646
17 Ma, Z. Y., Shen, Q. P., & Zhang, J. P. (2005). Application of 4D for dynamic site layout and management of construction projects. Autom Construct, 14(3), 369-381
https://doi.org/10.1016/j.autcon.2004.08.011
18 Steel, J., Drogemuller, R., & Toth, B. (2012). Model interoperability in building information modeling. Soft Syst. Model, 11(1), 99-109
https://doi.org/10.1007/s10270-010-0178-4
19 Yan, W., Culp, C., & Graf, R. (2011). Integrating BIM and gaming for real-time interactive architectural visualization. Autom Construct, 20(4), 446-458
https://doi.org/10.1016/j.autcon.2010.11.013
20 Zhong, D., Li, J., & Liu, K. (2003). Dynamic simulation technique for whole construction processes and its application to large-scale construction project. Journal of Tianjin University, 36(3), 347-52
[1] Mingyue LI, Zhuoling MA, Xi TANG. Owner-dominated building information modeling and lean construction in a megaproject[J]. Front. Eng, 2021, 8(1): 60-71.
[2] Hans VOORDIJK. Building information modeling and its impact on users in the lifeworld: a mediation perspective[J]. Front. Eng, 2019, 6(2): 193-206.
[3] Albert P. C. CHAN, Xiaozhi MA, Wen YI, Xin ZHOU, Feng XIONG. Critical review of studies on building information modeling (BIM) in project management[J]. Front. Eng, 2018, 5(3): 394-406.
[4] Takashi KANETA, Shuzo FURUSAKA, Nisi DENG. Overview and problems of BIM implementation in Japan[J]. Front. Eng, 2017, 4(2): 146-155.
[5] Dongping CAO, Heng LI, Guangbin WANG. Impacts of building information modeling (BIM) implementation on design and construction performance: a resource dependence theory perspective[J]. Front. Eng, 2017, 4(1): 20-34.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed