Critical review of studies on building information modeling (BIM) in project management
Albert P. C. CHAN1, Xiaozhi MA2(), Wen YI3, Xin ZHOU4, Feng XIONG5
1. Department of Building and Real Estate, Faculty of Construction and Environment, The Hong Kong Polytechnic University, Hong Kong, China
2. Department of Building and Real Estate, Faculty of Construction and Environment, The Hong Kong Polytechnic University, Hong Kong, China; College of Architecture and Environment, Sichuan University, Chengdu 610065, China
3. School of Engineering and Advanced Technology, College of Sciences, Massey University, Auckland, New Zealand
4. Department of Building and Real Estate, Faculty of Construction and Environment, The Hong Kong Polytechnic University, Hong Kong, China
5. College of Architecture and Environment, Sichuan University, Chengdu 610065, China
 Download: PDF(363 KB)   HTML
 Export: BibTeX | EndNote | Reference Manager | ProCite | RefWorks
Abstract

Building information modeling (BIM) and project management are two major research topics that accommodate large volumes of research efforts. BIM has been interpreted as a process technology that aids in enhancing project management. Hence, the investigation from an interdisciplinary perspective of the two concepts may bring new insights to understanding related research. In this paper, a structural approach is adopted in reviewing BIM studies in project management from 2005 to 2017 within identified target journals. This review aims to classify the major research directions and topics for BIM research in project management. Moreover, given BIM’s potential for application in project management, this paper attempts to establish a fundamental research foundation for a new paradigm of project management that incorporates BIM, namely, BIM-based project management. The preliminary result suggests that BIM research in project management develops drastically in the examined duration. The research directions of BIM studies in project management include enabling BIM as a technology in project management; BIM application as a solution for specific project management scopes; integration issues of BIM that have been brought to project management; institutional environment and regulatory governance of BIM in realizing project management strategies; and analysis of effects and strategies of BIM adoption and implementation in projects. The directions and trends are then analyzed to develop a research route for BIM studies in project management. Finally, conclusions focus on the relations of the research directions, as well as the contributions and theoretical implications of this review. Future research areas are also recommended.

Keywords building information modeling (BIM)      project management      review      BIM-based project management     
Corresponding Author(s): Xiaozhi MA   
Just Accepted Date: 09 July 2018   Online First Date: 20 August 2018    Issue Date: 14 September 2018
 Cite this article:   
Albert P. C. CHAN,Xiaozhi MA,Wen YI, et al. Critical review of studies on building information modeling (BIM) in project management[J]. Front. Eng, 2018, 5(3): 394-406.
 URL:  
https://academic.hep.com.cn/fem/EN/10.15302/J-FEM-2018203
https://academic.hep.com.cn/fem/EN/Y2018/V5/I3/394
Fig.1  Research framework
Target journals No. of papers found in the target journals No. of the final papers
AIC 31 30
JCEM 21 19
ITcon 17 12
IJPM 11 9
JCCE 8 7
AEI 4 4
CME 6 6
ECAM 9 8
JME 4 4
CI 2 2
PMJ 2 2
Total 115 103
Tab.1  Preliminary search and visual examination results in the target journals
Fig.2  Years of publication
Fig.3  Framework of mapping research directions of BIM research in project management
Research directions of BIM studies in project management Research topics
Enabling BIM as a technology in project management Development of BIM elements (e.g., modules, objects, and members);
Relations and connections among modules of BIM models;
Development of algorithms and tools;
Technical interoperability
BIM application as a solution for a specific project management scope Managing project objectives with BIM;
Applications of BIM for various tasks of project management;
BIM utilization in different stages of project management
Integration issues of BIM that have been brought to project management Information systems;
Cooperative interface approaches;
Integrated applications of BIM and other major ICTs
Institutional environment and regulatory governance of BIM to realize project management strategy Organizational changes brought by BIM;
New mechanism or context for cooperation and collaboration in projects;
Regulation and standardization
Analysis of the effects and strategies of BIM adoption and implementation in projects Effect of BIM on a project;
Analysis of project-wise BIM adoption;
BIM implementation in projects on a macro level
Tab.2  Summary of research areas of BIM in project management
Fig.4  Research route of BIM studies in project management
Park J., Cai H., Perissin D. 2018 JCCE
Pishdad-Bozorgi P., Gao X., Eastman C., Self A.P. 2018 AIC
Hamledari H., Rezazadeh Azar E., McCabe B. 2018 JCCE
Ma Z., Zhang D., Li J. 2018 AIC
Zhang L., Wen M., Ashuri B. 2018 JCCE
Pärn E.A., Edwards D.J., Sing M.C.P. 2018 AIC
Zhang S., Pan F., Wang C., Sun Y., Wang H. 2017 JCEM
Mansuri D., Chakraborty D., Elzarka H., Deshpande A., Gronseth T. 2017 AIC
Oraee M., Hosseini M.R., Papadonikolaki E., Palliyaguru R., Arashpour M. 2017 IJPM
Tezel A., Aziz Z. 2017 ITCon
Kehily D., Underwood J. 2017 ITCon
Kalasapudi V.S., Tang P., Turkan Y. 2017 AIC
Chang C.-Y., Pan W., Howard R. 2017 JCEM
Kifokeris D., Xenidis Y. 2017 JCEM
Niknam M., Karshenas S. 2017 AIC
Pärn E.A., Edwards D.J. 2017 AIC
Chen K., Lu W., Wang H., Niu Y., Huang G.G. 2017 JCEM
Chong H.-Y., Fan S.-L., Sutrisna M., Hsieh S.-H., Tsai C.-M. 2017 JCEM
Son H., Kim C., Kwon Cho Y. 2017 JME
He Q., Wang G., Luo L., Shi Q., Xie J., Meng X. 2017 IJPM
Park J., Cai H. 2017 AIC
Park C.-S., Kim H.-J., Park H.-T., Goh J.-H., Pedro A. 2017 IJPM
Cao D., Li H., Wang G., Huang T. 2017 IJPM
Zheng L., Lu W., Chen K., Chau K.W., Niu Y. 2017 IJPM
Kam C., Song M.H., Senaratna D. 2017 JCEM
Fuchs S., Scherer R.J. 2017 AIC
Zhang J., El-Gohary N.M. 2017 AIC
Davies K., McMeel D.J., Wilkinson S. 2017 ECAM
Franz B., Leicht R., Molenaar K., Messner J. 2017 JCEM
Edirisinghe R., London K.A., Kalutara P., Aranda-Mena G. 2017 ECAM
Tezel A., Aziz Z. 2017 ECAM
Murphy M.E., Nahod M.-M. 2017 ECAM
Mei T., Wang Q., Xiao Y., Yang M. 2017 ECAM
Wang J., Shou W., Wang X., Wu P. 2016 CME
Biagini C., Capone P., Donato V., Facchini N. 2016 AIC
Ciribini A.L.C., Mastrolembo Ventura S., Paneroni M. 2016 AIC
Poirier E., Forgues D., Staub-French S. 2016 CME
Ramaji I.J., Memari A.M. 2016 JCEM
Faghihi V., Reinschmidt K.F., Kang J.H. 2016 AIC
Kokkonen A., Alin P. 2016 CME
Niu Y., Lu W., Chen K., Huang G.G., Anumba C. 2016 JCCE
Fang Y., Cho Y.K., Zhang S., Perez E. 2016 JCEM
Isaac S., Bock T., Stoliar Y. 2016 AIC
Nepal M.P., Staub-French S. 2016 ITCon
Lu Q., Won J., Cheng J.C.P. 2016 IJPM
Dave B., Kubler S., Främling K., Koskela L. 2016 AIC
Zhang S., Teizer J., Pradhananga N., Eastman C.M. 2015 AIC
Costin A.M., Teizer J., Schoner B. 2015 ITCon
Oraskari J., Törmä S. 2015 AIC
Chen K., Lu W., Peng Y., Rowlinson S., Huang G.Q. 2015 IJPM
Chang C.-Y. 2015 IJPM
Patacas J., Dawood N., Vukovic V., Kassem M. 2015 ITCon
Lu W., Fung A., Peng Y., Liang C., Rowlinson S. 2015 JME
Khalili A., Chua D.K.H. 2015 JCCE
Kim H., Lee H.-S., Park M., Chung B., Hwang S. 2015 JCCE
Teizer J. 2015 AEI
Mäki T., Kerosuo H. 2015 CME
Rogers J., Chong H.-Y., Preece C. 2015 ECAM
Krystallis I., Demian P., Price A.D.F. 2015 CME
Alhava O., Laine E., Kiviniemi A. 2015 ITCon
Ding Z., Zuo J., Wu J., Wang J.Y. 2015 ECAM
Kähkönen K., Rannisto J. 2015 CI
Forsythe P., Sankaran S., Biesenthal C. 2015 PMJ
Li H., Lu M., Chan G., Skitmore M. 2015 AIC
Akanmu A., Anumba C.J. 2015 ECAM
Goulding J.S., Rahimian F.P., Wang X. 2014 ITCon
Choi B., Lee H.-S., Park M., Cho Y.K., Kim H. 2014 JCEM
Gelisen G., Griffis F.H. 2014 JCEM
Monteiro A., Mêda P., Poças Martins J. 2014 AIC
Boktor J., Hanna A., Menassa C.C. 2014 JME
Hanna A.S., Yeutter M., Aoun D.G. 2014 JCEM
Wu W., Issa R.R.A. 2014 JME
Lee S.-K., Kim K.-R., Yu J.-H. 2014 AIC
Chong H.-Y., Wong J.S., Wang X. 2014 AIC
Fernando Prof. T., Wu Dr. K.-C., Bassanino Dr. M. 2013 ITCon
Eadie R., Browne M., Odeyinka H., McKeown C., McNiff S. 2013 AIC
Hanna A., Boodai F., El Asmar M. 2013 JCEM
Aram S., Eastman C., Sacks R. 2013 AIC
Jiao Y., Wang Y., Zhang S., Li Y., Yang B., Yuan L. 2013 AEI
Lu W., Peng Y., Shen Q., Li H. 2013 JCEM
Alin P., Maunula A.O., Taylor J.E., Smeds R. 2013 PMJ
Hassan I. N. 2013 ITCon
Gökçe K.U., Gökçe H.U., Katranuschkov P. 2013 JCCE
Bryde D., Broquetas M., Volm J.M. 2013 IJPM
Ma Z., Wei Z., Zhang X. 2013 AIC
Bynum P., Issa R.R.A., Olbina S. 2013 JCEM
Chavada R., Dawood N., Kassem M. 2012 ITCon
Gustavsson T.K., Samuelson O., Wikforss Ö. 2012 ITCon
Brewer G., Gajendran T. 2012 CI
Bosché F. 2012 AEI
Golparvar-Fard M., Peña-Mora F., Savarese S. 2011 JCEM
Elbeltagi E., Dawood M. 2011 AIC
Scherer R.J., Schapke S.-E. 2011 AEI
Zhang J.P., Hu Z.Z. 2011 AIC
Hu Z., Zhang J. 2011 AIC
Sacks R., Koskela L., Dave B.A., Owen R. 2010 JCEM
Whyte J., Lobo S. 2010 CME
Sacks R., Radosavljevic M., Barak R. 2010 AIC
Popov V., Juocevicius V., Migilinskas D., Ustinovichius L., Mikalauskas S. 2010 AIC
Sacks R., Treckmann M., Rozenfeld O. 2009 JCEM
Leicht R., Messner J. 2008 ITCon
Fu C., Aouad G., Lee A., Mashall-Ponting A., Wu S. 2006 AIC
Sacks R., Navon R., Brodetskaia I., Shapira A. 2005 JCEM
  
1 Akanmu A, Anumba C J (2015). Cyber-physical systems integration of building information models and the physical construction. Engineering, Construction, and Architectural Management, 22(5): 516–535
https://doi.org/10.1108/ECAM-07-2014-0097
2 Alhava O, Laine E, Kiviniemi A (2015). Intensive big room process for co-creating value in legacy construction projects. In: Proceedings of 10th European Conference on Product and Process Modeling. 146–158
3 Alin P, Maunula A O, Taylor J E, Smeds R (2013). Aligning misaligned systemic innovations: Probing inter-firm effects development in project networks. Project Management Journal, 44(1): 77–93
https://doi.org/10.1002/pmj.21316
4 Aram S, Eastman C, Sacks R (2013). Requirements for BIM platforms in the concrete reinforcement supply chain. Automation in Construction, 35(35): 1–17
https://doi.org/10.1016/j.autcon.2013.01.013
5 Atkinson R, Crawford L, Ward S (2006). Fundamental uncertainties in projects and the scope of project management. International Journal of Project Management, 24(8): 687–698
https://doi.org/10.1016/j.ijproman.2006.09.011
6 Azhar S (2011). Building information modeling (BIM): Trends, benefits, risks, and challenges for the AEC industry. Leadership and Management in Engineering, 11(3): 241–252
https://doi.org/10.1061/(ASCE)LM.1943-5630.0000127
7 Björk B C (1989). Basic structure of a proposed building product model. Computer Aided Design, 21(2): 71–78
https://doi.org/10.1016/0010-4485(89)90141-3
8 Boktor J, Hanna A, Menassa C C (2014). State of practice of building information modeling in the mechanical construction industry. Journal of Management Engineering, 30(1): 78–85
https://doi.org/10.1061/(ASCE)ME.1943-5479.0000176
9 Bosch-Rekveldt M, Jongkind Y, Mooi H, Bakker H, Verbraeck A (2011). Grasping project complexity in large engineering projects: The TOE (Technical, Organizational and Environmental) framework. International Journal of Project Management, 29(6): 728–739
https://doi.org/10.1016/j.ijproman.2010.07.008
10 Bosché F (2012). Plane-based registration of construction laser scans with 3D/4D building models. Advanced Engineering Informatics, 26(1): 90–102
https://doi.org/10.1016/j.aei.2011.08.009
11 Brady T, Davies A (2014). Managing structural and dynamic complexity: A tale of two projects. Project Management Journal, 45(4): 21–38
https://doi.org/10.1002/pmj.21434
12 Brewer G, Gajendran T (2012). Attitudes, behaviours and the transmission of cultural traits: Impacts on ICT/BIM use in a project team. Construction Innovation, 12(2): 198–215
https://doi.org/10.1108/14714171211215949
13 Bröchner J, Björk B C (2008). Where to submit? Journal choice by construction management authors. Construction Management and Economics, 26(7): 739–749
https://doi.org/10.1080/01446190802017698
14 Bryde D, Broquetas M, Volm J M (2013). The project benefits of building information modelling (BIM). International Journal of Project Management, 31(7): 971–980
https://doi.org/10.1016/j.ijproman.2012.12.001
15 Cao D, Li H, Wang G (2014). Impacts of isomorphic pressures on BIM adoption in construction projects. Journal of Construction Engineering and Management, 140(12): 04014056
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000903
16 Cao D, Li H, Wang G, Huang T (2016). Identifying and contextualising the motivations for BIM implementation in construction projects: An empirical study in China. International Journal of Project Management, 35(4): 658–669
https://doi.org/10.1016/j.ijproman.2016.02.002
17 Chavada R, Dawood N, Kassem M (2012). Construction workspace management: The development and application of a novel nD planning approach and tool. Electronic Journal of Information Technology in Construction, 17(17): 213–236
18 Chen K, Lu W, Peng Y, Rowlinson S, Huang G Q (2015). Bridging BIM and building: From a literature review to an integrated conceptual framework. International Journal of Project Management, 33(6): 1405–1416
https://doi.org/10.1016/j.ijproman.2015.03.006
19 Choi B, Lee H S, Park M, Cho Y K, Kim H (2014). Framework for work-space planning using four-dimensional BIM in construction projects. Journal of Construction Engineering and Management, 140(9): 04014041
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000885
20 Chong H Y, Wong J S, Wang X (2014). An explanatory case study on cloud computing applications in the built environment. Automation in Construction, 44(8): 152–162
https://doi.org/10.1016/j.autcon.2014.04.010
21 Çıdık M S, Boyd D, Thurairajah N (2017). Ordering in disguise: Digital integration in built-environment practices. Building Research and Information, 45(6): 665–680
https://doi.org/10.1080/09613218.2017.1309767
22 Ciribini A L C, Mastrolembo Ventura S, Paneroni M (2016). Implementation of an interoperable process to optimise design and construction phases of a residential building: A BIM Pilot Project. Automation in Construction, 71(1): 62–73
https://doi.org/10.1016/j.autcon.2016.03.005
23 Costin A M, Teizer J, Schoner B (2015). RFID and BIM-enabled worker location tracking to support real-time building protocol control and data visualization. Journal of Information Technology in Construction, 20: 495–517
24 Darko A, Chan A P (2016). Critical analysis of green building research trend in construction journals. Habitat International, 57: 53–63
https://doi.org/10.1016/j.habitatint.2016.07.001
25 Dave B, Kubler S, Främling K, Koskela L (2016). Opportunities for enhanced lean construction management using Internet of Things standards. Automation in Construction, 61: 86–97
https://doi.org/10.1016/j.autcon.2015.10.009
26 Davies K, McMeel D J, Wilkinson S (2017). Making friends with Frankenstein: hybrid practice in BIM. Engineering, Construction, and Architectural Management, 24(1): 78–93
https://doi.org/10.1108/ECAM-04-2015-0061
27 Ding Z, Zuo J, Wu J, Wang J Y (2015). Key factors for the BIM adoption by architects: A China study. Engineering, Construction, and Architectural Management, 22(6): 732–748
https://doi.org/10.1108/ECAM-04-2015-0053
28 Eadie R, Browne M, Odeyinka H, McKeown C, McNiff S (2013). BIM implementation throughout the UK construction project lifecycle: An analysis. Automation in Construction, 36(1): 145–151
https://doi.org/10.1016/j.autcon.2013.09.001
29 Eastman C (1974). An Outline of the Building Description System. Research Report No. 50
30 Eastman C M (1999). Information exchange architectures for building models. Durability of building materials and components, 8: 2139–2156
31 Eastman C M, Teicholz P, Sacks R, Liston K (2011). BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors. New York: John Wiley & Sons
32 Elbeltagi E, Dawood M (2011). Integrated visualized time control system for repetitive construction projects. Automation in Construction, 20(7): 940–953
https://doi.org/10.1016/j.autcon.2011.03.012
33 Faghihi V, Reinschmidt K F, Kang J H (2016). Objective-driven and Pareto Front analysis: Optimizing time, cost, and job-site movements. Automation in Construction, 69: 79–88
https://doi.org/10.1016/j.autcon.2016.06.003
34 Fang Y, Cho Y K, Zhang S, Perez E (2016). Case study of BIM and cloud-enabled real-time RFID indoor localization for Construction Management Applications. Journal of Construction Engineering and Management, 142(7): 05016003
https://doi.org/10.1061/(ASCE)CO.1943-7862.0001125
35 Fernando T, Wu K C, Bassanino M (2013). Designing a novel virtual collaborative environment to support collaboration in design review meetings. Journal of Information Technology in Construction, 18: 372–396
36 Forsythe P, Sankaran S, Biesenthal C (2015). How far can BIM reduce information asymmetry in the Australian construction context? Project Management Journal, 46(3): 75–87
https://doi.org/10.1002/pmj.21504
37 Froese T M (2010). The impact of emerging information technology on project management for construction. Automation in Construction, 19(5): 531–538
https://doi.org/10.1016/j.autcon.2009.11.004
38 Fu C, Aouad G, Lee A, Mashall-Ponting A, Wu S (2006). IFC model viewer to support nD model application. Automation in Construction, 15(2): 178–185
https://doi.org/10.1016/j.autcon.2005.04.002
39 Gaddis P O (1959). The project manager. Harvard Business Review, 32(3): 89–97
40 Gelisen G, Griffis F H (2013). Automated productivity-based schedule animation: Simulation-based approach to time-cost trade-off analysis. Journal of Construction Engineering and Management, 140(4): B4013007
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000674
41 Gledson B J (2016). Hybrid project delivery processes observed in constructor BIM innovation adoption. Construction Innovation, 16(2): 229–246
https://doi.org/10.1108/CI-04-2015-0020
42 Gökçe K U, Gökçe H U, Katranuschkov P (2013). IFC-based product catalog formalization for software interoperability in the construction management domain. Journal of Computing in Civil Engineering, 27(1): 36–50
https://doi.org/10.1061/(ASCE)CP.1943-5487.0000194
43 Golparvar-Fard M, Peña-Mora F, Savarese S (2011). Integrated sequential as-built and as-planned representation with D 4AR tools in support of decision-making tasks in the AEC/FM industry. Journal of Construction Engineering and Management, 137(12): 1099–1116
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000371
44 Goulding J S, Rahimian F P, Wang X (2014). Virtual reality-based cloud BIM platform for integrated AEC projects. Journal of Information Technology in Construction, 19(19): 308–325
45 Gustavsson T K, Samuelson O, Wikforss Ö (2012). Organizing IT in construction: Present state and future challenges in Sweden. Electronic Journal of Information Technology in Construction, 17(17): 520–534
46 Hanna A, Boodai F, El Asmar M (2013). State of practice of building information modeling in mechanical and electrical construction industries. Journal of Construction Engineering and Management, 139(10): 47–54
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000747
47 Hanna A S, Yeutter M, Aoun D G (2014). State of practice of building information modeling in the electrical construction industry. Journal of Construction Engineering and Management, 30(1): 78–85
48 Hassan I N (2013). Reviewing the evidence: USE of digital collaboration technologies in major building and infrastructure projects. Journal of Information Technology in Construction, 18: 40–63
49 He Q, Wang G, Luo L, Shi Q, Xie J, Meng X (2016). Mapping the managerial areas of Building Information Modeling (BIM) using scientometric analysis. International Journal of Project Management, 35(4): 670–685
https://doi.org/10.1016/j.ijproman.2016.08.001
50 Isaac S, Bock T, Stoliar Y (2016). A methodology for the optimal modularization of building design. Automation in Construction, 65: 116–124
https://doi.org/10.1016/j.autcon.2015.12.017
51 Jiao Y, Wang Y, Zhang S, Li Y, Yang B, Yuan L (2013). A cloud approach to unified lifecycle data management in architecture, engineering, construction and facilities management: Integrating BIMs and SNS. Advanced Engineering Informatics, 27(2): 173–188
https://doi.org/10.1016/j.aei.2012.11.006
52 Jugdev K, Thomas J, Delisle C (2001). Rethinking project management–Old truths and new insights. In: Proceedings of Project Management Association Finland/Norwegian Project Management Forum
53 Jung Y, Joo M (2011). Building information modelling (BIM) framework for practical implementation. Automation in Construction, 20(2): 126–133
https://doi.org/10.1016/j.autcon.2010.09.010
54 Kähkönen K, Rannisto J (2015). Understanding fundamental and practical ingredients of construction project data management. Construction Innovation, 15(1): 7–23
https://doi.org/10.1108/CI-04-2014-0026
55 Ke Y, Wang S, Chan A P, Cheung E (2009). Research trend of public-private partnership in construction journals. Journal of Construction Engineering and Management, 135(10): 1076–1086
https://doi.org/10.1061/(ASCE)0733-9364(2009)135:10(1076)
56 Khalili A, Chua D K H (2015). IFC-based graph data model for topological queries on building elements. Journal of Computing in Civil Engineering, 29(3): 04014046
https://doi.org/10.1061/(ASCE)CP.1943-5487.0000331
57 Khan K I A, Flanagan R, Lu S L (2016). Managing information complexity using system dynamics on construction projects. Construction Management and Economics, 34(3): 1–13
https://doi.org/10.1080/01446193.2016.1190026
58 Kim H, Lee H S, Park M, Chung B, Hwang S (2015). Information retrieval framework for hazard identification in construction. Journal of Computing in Civil Engineering, 29(3): 04014052
https://doi.org/10.1061/(ASCE)CP.1943-5487.0000340
59 Kokkonen A, Alin P (2016). Practitioners deconstructing and reconstructing practices when responding to the implementation of BIM. Construction Management and Economics, 34(7–8): 578–591
https://doi.org/10.1080/01446193.2016.1164327
60 Lee S K, Kim K R, Yu J H (2014). BIM and ontology-based approach for building cost estimation. Automation in Construction, 41: 96–105
https://doi.org/10.1016/j.autcon.2013.10.020
61 Li H, Lu M, Chan G, Skitmore M (2015). Proactive training system for safe and efficient precast installation. Automation in Construction, 49: 163–174
62 Liu Y, van Nederveen S, Hertogh M (2017). Understanding effects of BIM on collaborative design and construction: An empirical study in China. International Journal of Project Management, 35(4): 686–698
https://doi.org/10.1016/j.ijproman.2016.06.007
63 Lu Q, Won J, Cheng J C P (2016). A financial decision making framework for construction projects based on 5D Building Information Modeling (BIM). International Journal of Project Management, 34(1): 3–21
https://doi.org/10.1016/j.ijproman.2015.09.004
64 Lu W, Fung A, Peng Y, Liang C, Rowlinson S (2015). Demystifying construction project time-effort distribution curves: BIM and Non-BIM comparison. Journal of Management Engineering, 31(6): 329–338
https://doi.org/10.1061/(ASCE)ME.1943-5479.0000356
65 Lu Y, Li Y, Skibniewski M, Wu Z, Wang R, Le Y (2014). Information and communication technology applications in architecture, engineering, and construction organizations: A 15-year review. Journal of Management Engineering, 31(1): A4014010
https://doi.org/10.1061/(ASCE)ME.1943-5479.0000319
66 Lundin R A, Söderholm A (1995). A theory of the temporary organization. Scandinavian Journal of Management, 11(4): 437–455
https://doi.org/10.1016/0956-5221(95)00036-U
67 Luo L, He Q, Jaselskis E J, Xie J (2017). Construction project complexity: Research trends and implications. Journal of Construction Engineering and Management, 143(7): 04017019
https://doi.org/10.1061/(ASCE)CO.1943-7862.0001306
68 Ma Z, Wei Z, Zhang X (2013). Semi-automatic and specification-compliant cost estimation for tendering of building projects based on IFC data of design model. Automation in Construction, 30(1): 126–135
https://doi.org/10.1016/j.autcon.2012.11.020
69 Mäki T, Kerosuo H (2015). Site managers’ daily work and the uses of building information modelling in construction site management. Construction Management and Economics, 33(3): 163–175
https://doi.org/10.1080/01446193.2015.1028953
70 Mancini M, Wang X, Skitmore M, Issa R (2017). Editorial for IJPM special issue on advances in building information modeling (BIM) for construction projects. International Journal of Project Management, 35(4): 656–657
https://doi.org/10.1016/j.ijproman.2016.12.008
71 Miettinen R, Paavola S (2014). Beyond the BIM utopia: Approaches to the development and implementation of building information modeling. Automation in Construction, 43: 84–91
https://doi.org/10.1016/j.autcon.2014.03.009
72 Mok K Y, Shen G Q, Yang R J (2017). Addressing stakeholder complexity and major pitfalls in large cultural building projects. International Journal of Project Management, 35(3): 463–478
https://doi.org/10.1016/j.ijproman.2016.12.009
73 Monteiro A, Mêda P, Poças Martins J (2014). Framework for the coordinated application of two different integrated project delivery platforms. Automation in Construction, 38(5): 87–99
https://doi.org/10.1016/j.autcon.2013.11.003
74 Murphy M E (2014). Implementing innovation: A stakeholder competency-based approach for BIM. Construction Innovation, 14(4): 433–452
https://doi.org/10.1108/CI-01-2014-0011
75 Nepal M P, Staub-French S (2016). Supporting knowledge-intensive construction management tasks in BIM. Journal of Information Technology in Construction, 21: 13–38
76 Niu Y, Lu W, Chen K, Huang G G, Anumba C (2016). Smart construction objects. Journal of Computing in Civil Engineering, 30(4): 04015070
https://doi.org/10.1061/(ASCE)CP.1943-5487.0000550
77 Oraskari J, Törmä S (2015). RDF-based signature algorithms for computing differences of IFC models. Automation in Construction, 57: 213–221
https://doi.org/10.1016/j.autcon.2015.05.008
78 Osei-Kyei R, Chan A P (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6): 1335–1346
https://doi.org/10.1016/j.ijproman.2015.02.008
79 Packendorff J (1995). Inquiring into the temporary organization: new directions for project management research. Scandinavian Journal of Management, 11(4): 319–333
https://doi.org/10.1016/0956-5221(95)00018-Q
80 Park C S, Kim H J, Park H T, Goh J H, Pedro A (2016). BIM-based idea bank for managing value engineering ideas. International Journal of Project Management, 35(4): 699–713
https://doi.org/10.1016/j.ijproman.2016.09.015
81 Patacas J, Dawood N, Vukovic V, Kassem M (2015). BIM for facilities management: Evaluating BIM standards in asset register creation and service life planning. Journal of Information Technology in Construction, 20: 313–331
82 PMBOK (2013). A Guide to the Project Management Body of Knowledge. Newtown Square : Project Management Institute
83 Poirier E, Forgues D, Staub-French S (2016). Collaboration through innovation: implications for expertise in the AEC sector. Construction Management and Economics, 34(11): 769–789
https://doi.org/10.1080/01446193.2016.1206660
84 Poirier E, Staub-French S, Forgues D (2015). Embedded contexts of innovation: BIM adoption and implementation for a specialty contracting SME. Construction Innovation, 15(1): 42–65
https://doi.org/10.1108/CI-01-2014-0013
85 Popov V, Juocevicius V, Migilinskas D, Ustinovichius L, Mikalauskas S (2010). The use of a virtual building design and construction model for developing an effective project concept in 5D environment. Automation in Construction, 19(3): 357–367
https://doi.org/10.1016/j.autcon.2009.12.005
86 Porwal A, Hewage K N (2013). Building Information Modeling (BIM) partnering framework for public construction projects. Automation in Construction, 31(5): 204–214
https://doi.org/10.1016/j.autcon.2012.12.004
87 Qazi A, Quigley J, Dickson A, Kirytopoulos K (2016). Project Complexity and Risk Management (ProCRiM): Towards modelling project complexity driven risk paths in construction projects. International Journal of Project Management, 34(7): 1183–1198
https://doi.org/10.1016/j.ijproman.2016.05.008
88 Ramaji I J, Memari A M (2016). Product architecture model for multistory modular buildings. Journal of Construction Engineering and Management, 142(10): 04016047
https://doi.org/10.1061/(ASCE)CO.1943-7862.0001159
89 Rogers J, Chong H Y, Preece C (2015). Adoption of Building Information Modelling technology (BIM): Perspectives from Malaysian engineering consulting services firms. Engineering, Construction, and Architectural Management, 22(4): 424–445
https://doi.org/10.1108/ECAM-05-2014-0067
90 Sacks R, Koskela L, Dave B A, Owen R (2010). Interaction of lean and building information modeling in construction. Journal of Construction Engineering and Management, 136(9): 968–980
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000203
91 Sacks R, Navon R, Brodetskaia I, Shapira A (2005). Feasibility of automated monitoring of lifting equipment in support of project control. Journal of Construction Engineering and Management, 131(5): 604–614
https://doi.org/10.1061/(ASCE)0733-9364(2005)131:5(604)
92 Scherer R J, Schapke S E (2011). A distributed multi-model-based Management Information System for simulation and decision-making on construction projects. Advanced Engineering Informatics, 25(4): 582–599
https://doi.org/10.1016/j.aei.2011.08.007
93 Sebastian R (2011). Changing roles of the clients, architects and contractors through BIM. Engineering, Construction, and Architectural Management, 18(2): 176–187
https://doi.org/10.1108/09699981111111148
94 Shenhar A J, Dvir D (1996). Toward a typological theory of project management. Research Policy, 25(4): 607–632
https://doi.org/10.1016/0048-7333(95)00877-2
95 Söderlund J (2004). Building theories of project management: past research, questions for the future. International Journal of Project Management, 22(3): 183–191
https://doi.org/10.1016/S0263-7863(03)00070-X
96 Succar B (2009). Building information modelling framework: A research and delivery foundation for industry stakeholders. Automation in Construction, 18(3): 357–375
https://doi.org/10.1016/j.autcon.2008.10.003
97 Succar B, Sher W, Williams A (2012). Measuring BIM performance: Five metrics. Architectural Engineering and Design Management, 8(2): 120–142
https://doi.org/10.1080/17452007.2012.659506
98 Svejvig P, Andersen P (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2): 278–290
https://doi.org/10.1016/j.ijproman.2014.06.004
99 Taylor J E, Bernstein P G (2009). Paradigm trajectories of building information modeling practice in project networks. Journal of Management Engineering, 25(2): 69–76
https://doi.org/10.1061/(ASCE)0742-597X(2009)25:2(69)
100 Wang X, Chong H Y (2015). Setting new trends of integrated Building Information Modelling (BIM) for construction industry. Construction Innovation, 15(1): 2–6
https://doi.org/10.1108/CI-10-2014-0049
101 Whyte J, Lobo S (2010). Coordination and control in project-based work: Digital objects and infrastructures for delivery. Construction Management and Economics, 28(6): 557–567
https://doi.org/10.1080/01446193.2010.486838
102 Wing C K (1997). The ranking of construction management journals. Construction Management and Economics, 15(4): 387–398
https://doi.org/10.1080/014461997372953
103 Wu W, Issa R R A (2014). BIM execution planning in green building projects: LEED as a use case. Journal of Management Engineering, 31(1): A4014007
https://doi.org/10.1061/(ASCE)ME.1943-5479.0000314
104 Yi W, Chan A P (2013). Critical review of labor productivity research in construction journals. Journal of Management Engineering, 30(2): 214–225
https://doi.org/10.1061/(ASCE)ME.1943-5479.0000194
105 Zhang S, Teizer J, Pradhananga N, Eastman C M (2015). Workforce location tracking to model, visualize and analyze workspace requirements in building information models for construction safety planning. Automation in Construction, 60(682): 74–86
https://doi.org/10.1016/j.autcon.2015.09.009
[1] Mingyue LI, Zhuoling MA, Xi TANG. Owner-dominated building information modeling and lean construction in a megaproject[J]. Front. Eng, 2021, 8(1): 60-71.
[2] Xiaoxiao XU, Patrick X. W. ZOU. System dynamics analytical modeling approach for construction project management research: A critical review and future directions[J]. Front. Eng, 2021, 8(1): 17-31.
[3] Qinghua HE, Junyan XU, Ting WANG, Albert P. C. CHAN. Identifying the driving factors of successful megaproject construction management: Findings from three Chinese cases[J]. Front. Eng, 2021, 8(1): 5-16.
[4] Algan TEZEL, Eleni PAPADONIKOLAKI, Ibrahim YITMEN, Per HILLETOFTH. Preparing construction supply chains for blockchain technology: An investigation of its potential and future directions[J]. Front. Eng, 2020, 7(4): 547-563.
[5] Yongkui LI, Qing YANG, Beverly PASIAN, Yan ZHANG. Project management maturity in construction consulting services: Case of Expo in China[J]. Front. Eng, 2020, 7(3): 384-395.
[6] Ibrahim Yahaya WUNI, Geoffrey Qiping SHEN, Bon-Gang HWANG. Risks of modular integrated construction: A review and future research directions[J]. Front. Eng, 2020, 7(1): 63-80.
[7] Elodie HOCHSCHEID, Gilles HALIN. Generic and SME-specific factors that influence the BIM adoption process: An overview that highlights gaps in the literature[J]. Front. Eng, 2020, 7(1): 119-130.
[8] Veronika BOLSHAKOVA, Annie GUERRIERO, Gilles HALIN. Identifying stakeholders’ roles and relevant project documents for 4D-based collaborative decision making[J]. Front. Eng, 2020, 7(1): 104-118.
[9] Yang YU, Jiafu TANG. Review of seru production[J]. Front. Eng, 2019, 6(2): 183-192.
[10] Mario VANHOUCKE. Planning projects with scarce resources: Yesterday, today and tomorrow’s research challenges[J]. Front. Eng, 2018, 5(2): 133-149.
[11] Takashi KANETA, Shuzo FURUSAKA, Nisi DENG. Overview and problems of BIM implementation in Japan[J]. Front. Eng, 2017, 4(2): 146-155.
[12] Jonathan Jingsheng SHI, Saixing ZENG, Xiaohua MENG. Intelligent data analytics is here to change engineering management[J]. Front. Eng, 2017, 4(1): 41-48.
[13] SangHyun LEE. Applying system dynamics to strategic decision making in construction[J]. Front. Eng, 2017, 4(1): 35-40.
[14] Shu-lin Zhang. Strengthening Project Management to Attain Overseas Blocks with High Potential for Exploration[J]. Front. Eng, 2016, 3(4): 331-337.
[15] Geert Letens,Kurt Verweire,Peter De Prins. Large Scale Infrastructure Projects: The Art of Project or Change Management?[J]. Front. Eng, 2016, 3(3): 197-202.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed